Is five years a current PJM service commitment?
No. It is the description in PJM’s September 2, 2025 educational presentation. Obtain the applicable utility and transmission owner’s current, site-specific service plan.
Power diligence guide
A large-load service timeline must separate application and verification, studies, agreements, infrastructure construction, and permission to energize. Use dated ERCOT or PJM guidance to identify the applicable process, then obtain the serving utility’s written initial-load and full-load schedule; a published study milestone is not a site energization commitment.

| Reference | Published timing | What it does not establish |
|---|---|---|
| PJM education, September 2, 2025, slide 27 | Described utility-led load connection as typically a five-year process. | A current site-specific promise, a universal regional average, or a generation-queue service standard. |
| ERCOT Planning Guide, July 11, 2026, §9.3.1 | Batch Zero submissions by July 24, 2026; study report by April 9, 2027. | An energization date. These are dated batch milestones, subject to subsequent process updates. |
| ERCOT notice, August 3, 2026 | Deferred the original August 7 classification notification pending verification. | Confirmation that an earlier calendar remained unchanged. |
| ERCOT notice, September 9, 2026 | Verification RFI responses within 10 business days; an extension of up to five business days could be requested. | A total application, study, construction, or energization duration. |
The PJM example is historical guidance, not a quotation of an enforceable service term. For present requirements, check the utility’s service documents and PJM’s current large-load process materials.
ERCOT’s July 8, 2026 notice ended further legacy LLIS reviews and approvals after July 10. The July 11 Planning Guide retains the former procedures in sections 9.8–9.10 expressly as legacy reference. Their short scoping and review intervals should not be presented as a generic current large-load connection schedule.
No current ERCOT-wide total duration is established by the references above. Ask for the applicable study schedule and a separate, evidence-backed construction and service plan. Read the load ramp and interconnection queue definitions, then use the site power-capacity guide to request the missing evidence.
No. It is the description in PJM’s September 2, 2025 educational presentation. Obtain the applicable utility and transmission owner’s current, site-specific service plan.
No. A report is a study milestone. Required commitments, infrastructure, testing, and energization approvals remain separate parts of the project schedule.
Do not assume so. The July 11, 2026 Planning Guide labels those procedures legacy. Confirm the active pathway, eligibility, and operative deadlines for the actual request.
No. They concern different rights and dependencies. Identify which process governs each part of a co-located or grid-supplied project.
Carry initial-load and full-load dates separately, with MW, service conditions, remaining dependencies, responsible parties, and the dated utility evidence supporting each milestone.